8.2 Consulting AG intensifies its efforts in production supervision at the "EnBW He Dreiht" offshore wind farm
With the start of installation of in total 64 wind turbines, 8.2 Consulting AG's inspection activities are entering the critical phase
The first wind turbine at the "EnBW He Dreiht" wind farm is installed! April 24, 2025 marks the "beginning of the end" of the global production work for Germany's largest offshore wind farm currently under construction some 110 kilometres west of Heligoland in the North Sea.
A milestone in the technological progress of the offshore industry has been reached with the V236-15.0 MW wind turbine, which is Vestas’ largest turbine available on the market with a rated power of 15 MW.